Use On Review

8-J-03-UR

Recommended for approval
by the Planning Commission

APPROVE the request for a surface mining and mineral extraction operation at this location as shown on the development plan and described in the plan of operation subject to 9 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. The proposed mining operation meeting all of the performance standards as contained in Article 4, Section 4.10 and Section 4.50 of the Knox County Zoning Ordinance.
2. Meeting all other applicable requirements of the Knox County Zoning Ordinance.
3. Obtain the required approval of this request from the Knox County Board of Commissioners.
4. Meeting the required 100' setback for the deposition of overburden or obtain a variance from the Knox County Board of Zoning Appeals to permit the placement of the material in the setback.
5. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
6. Meeting all applicable requirements and obtaining all required permits dealing with water and air quality from the appropriate governmental agency.
7. All traffic involved in the sales and distribution of the stone produced on this site will be limited to using the existing driveways on the west side on E. Gov. John Sevier Hwy.
8. Posting of the required bond with Knox County or the State of Tennessee.
9. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of grading permits.

Applicant Request

+

Property Information

+
Location
East side of E. Governor John Sevier Hwy., south side of Asbury Rd.

Commission District 8


Size
98.50 acres

Sector
East County

Currently on the Property
Quarry & vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the request for a surface mining and mineral extraction operation at this location as shown on the development plan and described in the plan of operation subject to 9 conditions
1. The proposed mining operation meeting all of the performance standards as contained in Article 4, Section 4.10 and Section 4.50 of the Knox County Zoning Ordinance.
2. Meeting all other applicable requirements of the Knox County Zoning Ordinance.
3. Obtain the required approval of this request from the Knox County Board of Commissioners.
4. Meeting the required 100' setback for the deposition of overburden or obtain a variance from the Knox County Board of Zoning Appeals to permit the placement of the material in the setback.
5. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
6. Meeting all applicable requirements and obtaining all required permits dealing with water and air quality from the appropriate governmental agency.
7. All traffic involved in the sales and distribution of the stone produced on this site will be limited to using the existing driveways on the west side on E. Gov. John Sevier Hwy.
8. Posting of the required bond with Knox County or the State of Tennessee.
9. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of grading permits.
Disposition Summary
APPROVE the request for a surface mining and mineral extraction operation at this location as shown on the development plan and described in the plan of operation subject to 9 conditions
Details of Action
1. The proposed mining operation meeting all of the performance standards as contained in Article 4, Section 4.10 and Section 4.50 of the Knox County Zoning Ordinance.
2. Meeting all other applicable requirements of the Knox County Zoning Ordinance.
3. Obtain the required approval of this request from the Knox County Board of Commissioners.
4. Meeting the required 100' setback for the deposition of overburden or obtain a variance from the Knox County Board of Zoning Appeals to permit the placement of the material in the setback.
5. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
6. Meeting all applicable requirements and obtaining all required permits dealing with water and air quality from the appropriate governmental agency.
7. All traffic involved in the sales and distribution of the stone produced on this site will be limited to using the existing driveways on the west side on E. Gov. John Sevier Hwy.
8. Posting of the required bond with Knox County or the State of Tennessee.
9. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of grading permits.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.
After the Planning Commission
Because of its location in the County, appeals will be heard by County Commission.
County Commission
August 25, 2003
Appeal by: September 13, 2003

The appeal deadline - September 13, 2003 - has passed.

The Process
Applicant

Rinker Materials South Central, Inc.


Case History