APPROVE the amendment to 10-H-06-UR and 6-H-09-UR to permit night time operation of an asphalt mixing plant at this location as required by government contracts subject to 7 conditions


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
North side of E. Raccoon Valley Dr., northeast of I-75

Commission District 7


Size
216 acres

Sector
North County

Land Use Designation? Agricultural / Rrural Residential


Currently on the Property
Asphalt mixing plant

Growth Plan
Rural Area

Case Notes

+
Staff Recommendation
APPROVE the amendment to 10-H-06-UR and 6-H-09-UR to permit night time operation of an asphalt mixing plant at this location as required by government contracts subject to 7 conditions
1. Meeting all applicable requirements of the Knox County Health Dept.
2. No access from the asphalt mixing plant site to Gamble Rd.
3. The roadway providing access to this site will either be paved or constructed with an all weather driving surface. The paved section of the access road shall extend through the commercially zoned property.
4. Meeting all requirements and obtaining all required water and air quality permits from the applicable State and Federal agencies
5. Meeting all requirements of performance standards contained in Article 4.10 and all other applicable requirements of the Knox County Zoning Ordinance
6. Implementing the measures as required by 6-H-09-UR as contained in "Information Regarding Operation of Asphalt Plant at Raccoon Valley Quarry of USA Aggregates" prior to continued night time operations
7 Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.

With the conditions noted, this plan meets the requirement in the I (Industrial) zone and the other criteria for approval of a use on review
Disposition Summary
APPROVE the amendment to 10-H-06-UR and 6-H-09-UR to permit night time operation of an asphalt mixing plant at this location as required by government contracts subject to 7 conditions

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - August 7, 2010 - has passed.

The Process
Applicant

APAC Atlantic, Inc.


Case History