Details of Action
−
+
1) The applicant shall coordinate with TVA on the construction of the tower since it is close to TVA's power transmission lines.
2) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5) A revised site plan reflecting the conditions of approval must be submitted to MPC prior to the issuance of building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.
Property Information
−
+
Location3831 Copper Ridge Rd
West side of Copper Ridge Rd., southwest of Valleybrook Dr.
Commission District 6
Size54 acres
Sector
Currently on the Property
Church camp and vacant land
Growth PlanPlanned Growth Area
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a 250 foot lattice-work telecommunications tower subject to 5 conditions.
1) The applicant shall coordinate with TVA on the construction of the tower since it is close to TVA's power transmission lines.
2) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5) A revised site plan reflecting the conditions of approval must be submitted to MPC prior to the issuance of building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.
Disposition Summary
APPROVE the development plan for a 250 foot lattice-work telecommunications tower subject to 5 conditions.
Details of Action
1) The applicant shall coordinate with TVA on the construction of the tower since it is close to TVA's power transmission lines.
2) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5) A revised site plan reflecting the conditions of approval must be submitted to MPC prior to the issuance of building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.