Details of Action
−
+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
With the conditions noted above, this request meets all requirements for approval in the SC zoning district, and other criteria for approval of a use on review.
Property Information
−
+
Location7216 Chapman Hwy
North side of Chapman Hwy, east of Nixon Rd.
Commission District 9
Size0.85 acre
SectorLand Use Designation? Commercial
Currently on the Property
Vacant land and parking lot
Growth PlanUrban Growth Area
- Utilities
SewerKnox-Chapman Utility District
WaterKnox-Chapman Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the development plan, subject to 4 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
With the conditions noted above, this request meets all requirements for approval in the SC zoning district, and other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan, subject to 4 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.