Details of Action
−
+
1. Meeting all applicable requirements of the Knoxville Department of Engineering.
2. Connecting the development to sanitary sewer, and meeting all other applicable requirements of the Knox County Health Department.
3. Meeting all requirements of the Knoxville Zoning Ordinance.
4. Meeting all requirements of the City of Knoxville Arborist.
5. Installing all landscaping, as shown on the plan, within six months of issuance of occupancy permits for the project.
6. Obtaining approval of the requested variances from Knoxville Board of Zoning Appeals (8-M-04-VA).
With the conditions noted above, this request meets all requirements for approval in the R-1A zone, as well as other criteria for approval of a use-on-review.
Property Information
−
+
Location2504 Cecil Ave
South side of Cecil Ave., west of N. Cherry St.
Council District 4
Size2 acres
Sector
Currently on the Property
Church, parking and residence
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for the church building and parking lot expansion, subject to 6 conditions:
1. Meeting all applicable requirements of the Knoxville Department of Engineering.
2. Connecting the development to sanitary sewer, and meeting all other applicable requirements of the Knox County Health Department.
3. Meeting all requirements of the Knoxville Zoning Ordinance.
4. Meeting all requirements of the City of Knoxville Arborist.
5. Installing all landscaping, as shown on the plan, within six months of issuance of occupancy permits for the project.
6. Obtaining approval of the requested variances from Knoxville Board of Zoning Appeals (8-M-04-VA).
With the conditions noted above, this request meets all requirements for approval in the R-1A zone, as well as other criteria for approval of a use-on-review.
Disposition Summary
APPROVE the development plan for the church building and parking lot expansion, subject to 6 conditions:
Details of Action
1. Meeting all applicable requirements of the Knoxville Department of Engineering.
2. Connecting the development to sanitary sewer, and meeting all other applicable requirements of the Knox County Health Department.
3. Meeting all requirements of the Knoxville Zoning Ordinance.
4. Meeting all requirements of the City of Knoxville Arborist.
5. Installing all landscaping, as shown on the plan, within six months of issuance of occupancy permits for the project.
6. Obtaining approval of the requested variances from Knoxville Board of Zoning Appeals (8-M-04-VA).
With the conditions noted above, this request meets all requirements for approval in the R-1A zone, as well as other criteria for approval of a use-on-review.