Details of Action
−
+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
3. Meeting all applicable requirements of the Knox County Fire Marshall
4. Prior to commencing grading, provide a detailed landscaping plan to MPC staff for review and approval. All landscaping shown on the approved plan must be installed within 6 months of the issuance of an occupancy permit
5. The proposed driveway to the site shall not exceed a grade of 15%
Property Information
−
+
LocationSouth side of Hardin Valley Rd., south of Willow Point Wy.
Commission District 6
Size17.17 acres
SectorLand Use Designation? C (Commercial), SLPA (Slope protection) & LDR (Low density residential)
Currently on the Property
Vacant land
Growth PlanPlanned Growth Area
- Utilities
SewerWest Knox Utility District
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the request for a sports training facility on this site as shown on the development plan subject to 5 conditions
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
3. Meeting all applicable requirements of the Knox County Fire Marshall
4. Prior to commencing grading, provide a detailed landscaping plan to MPC staff for review and approval. All landscaping shown on the approved plan must be installed within 6 months of the issuance of an occupancy permit
5. The proposed driveway to the site shall not exceed a grade of 15%
Disposition Summary
APPROVE the request for a sports training facility on this site as shown on the development plan subject to 5 conditions
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
3. Meeting all applicable requirements of the Knox County Fire Marshall
4. Prior to commencing grading, provide a detailed landscaping plan to MPC staff for review and approval. All landscaping shown on the approved plan must be installed within 6 months of the issuance of an occupancy permit
5. The proposed driveway to the site shall not exceed a grade of 15%