Recommended for approval
by the Planning Commission

APPROVE the development plan in the SC and C-4 zoning districts, subject to 4 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting any other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.

Applicant Request

+

Property Information

+
Location
7210 Chapman Hwy

North side Chapman Hwy., southeast of Nixon Rd.

Commission District 9
Census Tract 55


Size
1.08 acres

Sector
South County

Land Use Designation? Commercial


Currently on the Property
Vacant restaurant

Growth Plan
Urban Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan in the SC and C-4 zoning districts, subject to 4 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting any other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.

With the conditions noted above, this request meets all requirements of the SC and C-4 zoning districts, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan in the SC and C-4 zoning districts, subject to 4 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting any other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - January 10, 2004 - has passed.

The Process
Applicant

Michael Brady, Inc. - Paul Anastasio