Row Closure

12-C-01-SC

Recommended for approval
by the Planning Commission

APPROVE subject to any easements required


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

This portion of right-of-way was abandoned by the State of Tennessee when the new Middlebrook Pike alignment was completed and is no longer needed for public access.

Close Street From
South side new Middlebrook Pike right-of-way
To
north side of parcel 094-IF-15
Reason for Closure
This portion of right-of-way was abandoned by the State of Tennessee when the new Middlebrook Pike alignment was completed and is no longer needed for public access.
Objections

Bell South and KUB request easement for existing utilities.


Property Information

+
Location
0 Old Middlebrook Pike

Council District 3


Sector
Central City

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the closure of this portion of right-of-way subject to any easements required.
This section of Middlebrook Pike was realigned during its construction to a four lane median divided facility which resulted in this portion of right-of-way no longer being needed. This closure will permit its incorporation into the adjoining parcel.
Disposition Summary
APPROVE subject to any easements required

What's next?

+
After the Planning Commission
This Row Closure case in the City was recommended for approval. The appeal deadline - December 28, 2001 has passed.
Applicant

City of Knoxville


Case History