Details of Action
−
+
1. Meeting all applicable requirements of the approved concept plan.
2. Installation of a 4' wide sidewalk on at least one side of all internal streets. All sidewalk construction is to be ADA compliant.
3. Installation of landscaping shown on the development plan within six months of the issuance of the first occupancy permit for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Meeting all applicable requirements of the Knox County Zoning Ordinance.
5. A revised site plan reflecting conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for this unit of Copperstone Subdivision for up to 85 detached single family dwellings on individual lots subject to 5 conditions
1. Meeting all applicable requirements of the approved concept plan.
2. Installation of a 4' wide sidewalk on at least one side of all internal streets. All sidewalk construction is to be ADA compliant.
3. Installation of landscaping shown on the development plan within six months of the issuance of the first occupancy permit for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Meeting all applicable requirements of the Knox County Zoning Ordinance.
5. A revised site plan reflecting conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
Disposition Summary
APPROVE the development plan for this unit of Copperstone Subdivision for up to 85 detached single family dwellings on individual lots subject to 5 conditions
Details of Action
1. Meeting all applicable requirements of the approved concept plan.
2. Installation of a 4' wide sidewalk on at least one side of all internal streets. All sidewalk construction is to be ADA compliant.
3. Installation of landscaping shown on the development plan within six months of the issuance of the first occupancy permit for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Meeting all applicable requirements of the Knox County Zoning Ordinance.
5. A revised site plan reflecting conditions of approval must be submitted to MPC staff prior to issuance of any building permits.