Use On Review

11-A-01-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a heating and air conditioning business at this location, subject to 8 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the City of Knoxville Zoning Ordinance.
2. Meeting all requirements of the City of Knoxville Department of Engineering.
3. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for this project.
4. Meeting all requirements of the City of Knoxville Arborist.
5. Meeting all requirements of the Knox County Health Department.
6. Adhering to the stipulations indicated in the submitted letter from the applicant, dated December 26, 2001.
7. All business activities shall take place inside the building.
8. No outdoor storage of materials will be permitted on the site.

Applicant Request

+

Property Information

+
Location
4108 Central Avenue Pike

Southwest side of Central Avenue Pike, southeast of Bookwalter Dr.

Council District 5


Size
1.26 acres

Sector
North City

Land Use Designation? Medium Density Residential


Currently on the Property
Vacant land

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the development plan for a heating and air conditioning business at this location, subject to 8 conditions:
1. Meeting all applicable requirements of the City of Knoxville Zoning Ordinance.
2. Meeting all requirements of the City of Knoxville Department of Engineering.
3. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for this project.
4. Meeting all requirements of the City of Knoxville Arborist.
5. Meeting all requirements of the Knox County Health Department.
6. Adhering to the stipulations indicated in the submitted letter from the applicant, dated December 26, 2001.
7. All business activities shall take place inside the building.
8. No outdoor storage of materials will be permitted on the site.

With the conditions noted above, this request meets all requirements for approval in the C-3 zoning district, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a heating and air conditioning business at this location, subject to 8 conditions:
Details of Action
1. Meeting all applicable requirements of the City of Knoxville Zoning Ordinance.
2. Meeting all requirements of the City of Knoxville Department of Engineering.
3. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for this project.
4. Meeting all requirements of the City of Knoxville Arborist.
5. Meeting all requirements of the Knox County Health Department.
6. Adhering to the stipulations indicated in the submitted letter from the applicant, dated December 26, 2001.
7. All business activities shall take place inside the building.
8. No outdoor storage of materials will be permitted on the site.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - January 25, 2002 - has passed.

The Process