Details of Action
−
+
1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
2. Installing all internal traffic control measures as shown on the site plan prior to issuance of an occupancy permit for the fueling center
3. Meeting all applicable requirements of the City of Knoxville Dept. of Engineering
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff for certification prior to issuance of a building permit
Property Information
−
+
Location5753 Western Ave
North side of Western Avenue, west of Palmetto Road
Council District 3
Census Tract 47
Size4.05 acres
SectorLand Use Designation? C (Sector Plan), GC (One Year Plan)
Currently on the Property
Shopping center
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the request for a fueling station as shown on the site plan subject to 4 conditions
1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
2. Installing all internal traffic control measures as shown on the site plan prior to issuance of an occupancy permit for the fueling center
3. Meeting all applicable requirements of the City of Knoxville Dept. of Engineering
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff for certification prior to issuance of a building permit
Disposition Summary
APPROVE the request for a fueling station as shown on the site plan subject to 4 conditions
Details of Action
1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
2. Installing all internal traffic control measures as shown on the site plan prior to issuance of an occupancy permit for the fueling center
3. Meeting all applicable requirements of the City of Knoxville Dept. of Engineering
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff for certification prior to issuance of a building permit